Close

Request A Callback

If you would like one of our representatives to give you a call to discuss your situation in complete confidence, please enter your details below and someone will call you as soon as possible.

[[[["field5","not_equal_to","I consent for my data to be used by Mediatelegal to process my enquiry."]],[[]],"and"]]
1
Your Name
Phone Number
Previous
Next

Costain v Tarmac – dispute resolution procedures in multiple NEC3 contracts

Costain v Tarmac – the issue of different dispute resolution procedures in two contracts was the focus of a recent TCC case.

The problem of defective concrete in newly-installed central reservation barriers on the M1 in Nottinghamshire was well-documented at the time in 2015.

Main contractor Costain was party to an NEC Framework Agreement with the Secretary of State for Transport for the provision of transport infrastructure projects. Separately, Tarmac was party to another NEC Framework Agreement with the Secretary of State for the provision of construction materials. Costain was obliged to seek proposals from Tarmac for the provision of ready mix concrete, which it did.

Costain subsequently placed a subcontract with Tarmac for the provision of concrete to slipform the new barriers. That subcontract used the NEC Supply Short Contract (SSC).

The Parties’ relationship was therefore governed by all three contracts.

The Parties’ dispute concerned the difference between the cost of the remedial works which Tarmac accepted, and the cost of the (more extensive) remedial works proposed by Costain. That was referred to adjudication. The adjudicator was Christopher Hough, nominated by the ICE. He decided that Costain was out of time to pursue the claim. Costain was seeking to recover £6 million by way of damages for breach of contract.

Differences in the dispute resolution provisions of the Framework Agreement and the Subcontract were highlighted by Costain as part of its arguments to avoid the adjudicator’s decision. This case in the TCC concerned the ability of Tarmac to refer the dispute to arbitration. Costain’s case concerned a number of issues which are discussed in the judgment here.

Tarmac said that although there was only one overall sub-contract, the existence of two separate sets of contract conditions was relevant. Tarmac said that a dispute between the parties under the Framework Contract (which would relate to the seeking of the quotation and the provision of the quotation) would be governed by the Framework Agreement’s provisions, whereas any dispute as to the supply of the concrete itself would be governed by the specific adjudication/arbitration clause 93 of the Supply Contract.

The Judge “reached the firm conclusion that [Tarmac’s] interpretation of the contract [was] the correct one.”

He further commented, “Thus, the fact that there were two separate sets of NEC3 conditions was a deliberate decision which reflected the two elements of the relationship between the parties. In those circumstances, the fact that the parties had agreed that those two separate aspects of their relationship required two different dispute resolution provisions is unexceptionable. The conclusion that, in this case, there were two separate dispute resolution procedures which did not overlap but complemented each other, because they related to two separate elements of the relationship between the parties…”

Conclusion

The use of the NEC Framework Contract is widespread with many major industry clients who prefer frameworks to repeated procurement of individual contracts. This case has highlighted the need for the parties to such agreements to ensure that the terms are well-drafted, particularly where Z clauses or their equivalents under other standard forms of contract are concerned.

Costain Limited v Tarmac Holdings [2017] EWHC 319 (TCC)

 

Tagged with: , , , ,
Posted in case studies, Construction

Leave a Reply

Your email address will not be published. Required fields are marked *

*

Did you know?

Workplace disputes will affect profitability and performance. Use mediation to resolve disputes swiftly.

The longer a dispute continues in the workplace, the more dramatic the effect on those working in or around it.

Conflict between employees can spread throughout the workforce, affecting morale and performance, if untreated.

A 2008 CIPD survey found that 51% of respondents use an external mediator to resolve people problems and conflict.

A 2008 CIPD survey found that 75% of mediations were initiated by HR departments.

If you express your anger you will start an argument; if you explain your anger you will start a discussion.

In 2016 mediation will have saved UK businesses £3 billion in wasted management time & productivity, damaged relationships, & legal fees.

Ignoring ‘mega-cases’ the total value of mediated disputes in the UK each year is £11.5 billion.

Since 1990, the total value of mediated cases in England & Wales is £110 billion.

CEO of regional Charity – “We have had cause to use Mediatelegal recently and I was delighted with their service. the mediator was patient during a very emotional and somewhat difficult situation but handled it beautifully. We saved a significant amount of money and would highly recommend this organisation to anyone wishing to avoid costly legal bills.”

Linda Lavery, The HR Dept: “I cannot recommend them highly enough. They were brought in to resolve a complex dispute which had continued for months with no resolution. The process was managed from start to finish by Mediatelegal and with their expertise and impartiality, the conflict was resolved amicably for all parties in just 1 day. The management time and money that has been saved is incalculable.”

According to the CEDR 2018 audit, 89% of mediations settle successfully on the day or shortly afterwards.

You are entitled to recover certain expenses incurred when attending a SEND mediation session.

An individual might potentially require an Education, Health and Care Plan (EHCP until they reach the age of 25.

| Website designed & hosted by Cyberfrog Design
Mediatelegal is a trading style of Why Mediate Ltd (Company Reg No. 09148466)
Cookies | Terms & Conditions